Standardize what comes in
Clarify eligibility, school intake, vendor information, budget inputs, and allowability review before requests enter contracting.
PROGRAM OPERATIONS / Tennessee Department of Education
A statewide process that scaled vendor contracts from about 30 to 900+ across a $146.5M portfolio.
SEE THE WORK
A tracker every team worked from, and a signature route that replaced paper.
| A | B | C | D | E | F | G | H | I | J | |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Contract ID | School | Service category | Grants ID | Amount | Allowability | Vendor packet | Status | PO # | Paid to date |
| 2 | EANS-23-0388 | Tutoring services | EP-11824 | $42,600.00 | Approved | Complete | Paid | PO-7710 | $42,600.00 | |
| 3 | EANS-23-0391 | Instructional technology | EP-11830 | $18,450.00 | Approved | Complete | Paid | PO-7714 | $18,450.00 | |
| 4 | EANS-23-0402 | Counseling services | EP-11857 | $27,900.00 | Approved | Complete | Out for signature | $0.00 | ||
| 5 | EANS-23-0407 | Educational software | EP-11862 | $9,875.00 | Approved | Complete | Out for signature | $0.00 | ||
| 6 | EANS-23-0411 | Sanitation supplies | EP-11871 | $6,240.00 | Returned | Missing W-9 | Hold: see notes | $0.00 | ||
| 7 | EANS-23-0412 | Instructional technology | EP-11873 | $31,120.00 | Approved | Complete | Ready for signature | $0.00 | ||
| 8 | EANS-23-0415 | Tutoring services | EP-11880 | $15,300.00 | In review | Complete | In review | $0.00 | ||
| 9 | EANS-23-0419 | Professional development | EP-11886 | $12,000.00 | In review | Pending | In review | $0.00 |
Recreation of the working tracker, rebuilt with fictional contract IDs, amounts, and redacted school names. The real workbook held every contract from intake through payment, and it was the shared source of truth across teams.
Route: School confirms → Vendor signs → Commissioner signs
Recreation of the e-signature route I introduced to replace paper routing, with fictional contract data. The order reflects the real process: the school and vendor identified the need, my team authored the contract from the vendor’s figures, the school confirmed, and the vendor and the Commissioner signed.
THE STARTING POINT
Schools identified their needs and vendors, but the state contracted with and paid those vendors directly. Delivery depended on connected work across grants, finance, procurement, contracting, legal, and executive leadership. Unclear processes and limited capacity constrained that work.
THE WORK
Clarify eligibility, school intake, vendor information, budget inputs, and allowability review before requests enter contracting.
Build a repeatable path through contract preparation, review, approval, purchase orders, invoicing, and payment.
Work across functional teams whose members did not report to me, resolving bottlenecks and maintaining shared progress.
Support schools and vendors with consistent guidance and expenditure monitoring.
BEFORE AI
I didn’t use AI for this work. I scaled it with automation instead: introducing e-signature routing for contracts that had moved on paper, and building Excel models to track eligibility, allocations, and contract status across hundreds of transactions.
THE RESULT
The funding figure describes program scope. Contract counts describe execution volume; they are not a measure of annual revenue or funds personally awarded. The $63 million follow-on redeployed unspent EANS funds and is not additional to the $146.5 million.